Platform / System foundations
Energy is a system.
Plan it that way.
A project’s energy requirement is more than a single capacity figure. Start with demand, follow the physical flows, and identify the information each decision needs.
SupplyGeneration & procurement
NetworksTransmission & distribution
UseIndustry, buildings & transport
Flexibility + informationStorage · Demand response · Measurement · Software
01 / SupplyCapacity is not annual production.
A 10 MW generator does not produce 10 MW continuously. Annual output depends on availability, weather, maintenance and curtailment. A capacity factor converts rated power into an annual energy estimate; it does not establish when energy is available.
Ask forTechnology, location, hourly production profile, connection limit, curtailment assumptions and commercial terms.
02 / ConnectThe grid connection sets real boundaries.
Import and export limits, voltage, reinforcement works, protection and connection timing can shape what a project can deliver. Annual energy balance alone says little about connection feasibility.
Ask forNetwork operator confirmation, capacity allocation, proposed connection date, single-line diagram and applicable technical studies.
03 / BalanceStorage has both power and energy limits.
MW describes the rate of battery discharge. MWh describes stored energy. Usable fraction, discharge efficiency, degradation and reserve settings reduce the energy available to a site. Demand response changes when energy is used and requires an achievable operating plan.
Ask forCritical load, required duration, usable state-of-charge window, discharge efficiency, inverter rating, degradation allowance and recharge strategy.
04 / UseThe load profile is the starting point.
Peak demand sizes infrastructure; average demand determines energy use. Interval meter readings, operating hours and production patterns help identify peaks, flexible processes and critical circuits. Future electrification should be listed separately from today's measured demand.
Ask forTwelve months of interval data, forecast additions, critical circuits, outage tolerance and any seasonal operating constraints.
05 / InformationConnect data before automating decisions.
Define data ownership, access permissions, asset identifiers and cyber requirements before selecting a software layer. Integration and operational control require validation beyond a browser planning tool.
Conceptual guidance, not a grid study or a design specification. Sources and context →